Current & Future Projects



2024

     

Allouez Ave
Hazen Road to USH 141 (Main St.)

UPDATE: Thursday, June 20, 2024

The Wisconsin Department of Transportation Northeast Region (WisDOT) is announcing that work will begin on Allouez Avenue, from Hazen Road to USH 141 (Main Street) in the Village of Bellevue. The roadway will be closed over the next few months to replace the pavement and add sidewalk throughout the project. The project will consist of grading, storm sewer, pavement replacement, concrete pavement bridge approaches, curb and gutter, sidewalk, pavement markings, signing, and new pedestrian crossing.

CONSTRUCTION TIMELINE
May 20, 2024 - August 9, 2024

Week of 06/24/2024
Vinton will have the 300-ft stream realignment work east of I-43 on the north side of Allouez Ave completed by the end of this week. Vinton’s pipe crew completed storm sewer outfalls west of the I-43 bridge early in the week. The 60-Inch diameter concrete culvert was finished Wednesday, June 26. Roadway excavation and grading will continue working east from Little Creek Ln to Meadow Park Dr into next week to finish up reconstruction of the road base. Martell placed concrete sidewalk from Hazen Road to the I-43 bridge along the north side of Allouez Ave on Thursday.


Week of 07/01/2024
This will be a short week with Independence Day work restrictions beginning at noon on Wednesday, July 3rd and running through 6:00 am Monday, July 8th. Martell will continue work on the west half of the project placing curb and gutter along the north side of Allouez Avenue and filling in gaps of curb and sidewalk at intersections. Vinton will address grading for roadway, sidewalk, and slopes throughout the week. The pipe crew will complete storm sewer outfalls east of the I-43 bridge that discharge to the realigned stream. Smith restoration will place seed and erosion matting on slopes the are prepared with topsoil to allow vegetation to start germinating over the long weekend.


Maps
June - Detour Map of Allouez Ave.
May - Allouez Avenue Construction Access
             

Traffic Impacts
Allouez Avenue will be closed to through traffic with access for local traffic only. The posted detour route utilizes Lime Kiln Road, Verlin Road, and USH 141 (Main St).

There will be no through access on the project due to the grade differential at the I-43 bridge at times. Residents must access areas west of the bridge from Hazen Road and east of the bridge from USH 141 (Main Street).

Contact:
Katie Schwartz, P.E.,
WisDOT Project Manager
[email protected]
(920) 492-5652

Ben DeBaker, P.E.,
Construction Engineer – Ayres
[email protected]
(262) 844-7777

Teal Spellman, P.E.,
Bellevue Director of Public Works
[email protected]
(920) 593-5507


2024

     

Pavement Reconstruction - Verlin Rd. - A-24 

UPDATE: Thursday, June 20, 2024

Construction consists of roadway resurfacing on Verlin Road between Bellevue Street and Lime Kiln Road, trail resurfacing along portions of the East River Trail and construction of new tennis/pickleball courts at DeBroux Park.

CONSTRUCTION TIMELINE
May 2024 - September 2024

Week of 06/24/2024

Concrete curb and gutter along with sidewalk pours on Verlin Road. Continuation of base repair and completion of the lower layer of asphalt on the sports courts at DeBroux Park.

Week of 07/01/2024
Asphalt removal and start of roadway grading on Verlin Road between Lime Kiln Road and Seville Drive.

Important Upcoming Dates
05/28/2024 - Start of Construction at DeBroux Park
06/10/2024 - Start of Construction on Verlin Road
08/14/2024 - End of Construction on Verlin Road. Start of East River Trail
09/09/2024 - Completion of work

             

Road Closures, Vehicles & Traffic
For construction on Verlin Road, the road will be closed to Thru Traffic with a signed detour route. Residents who reside in the closure will be able to access their residence, but slight delays may be encountered due to construction equipment using the area. Be attentive of construction workers through the construction zone. The East River Trail portions will be closed during construction.

Business Access
Business access will be maintained as much as possible during construction. We intend to keep driveways open to each business at all times but may need to temporarily close one due to curb and gutter replacements. Prior communication will occur if access will be unobtainable. Please contact the Construction Manager if you require special access needs.


Communication:
It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation @920-491-9081. As project manager, Cedar is most familiar with the daily operations of construction and can resolve many issues quickly.

If something happens after normal work hours that you feel requires immediate attention, please contact our On-Call Laborer @ 920-371-0744, and arrangements will be made to resolve the issue. As always, in an emergency, please call 911.


2024

     

Utility Construction
Skyview Street and Vanden Bergh Place – B-24

 

UPDATE: Thursday, June 20, 2024

Construction consists of water main replacement and water and sewer service replacements to the right of way at previously identified properties. Upon completion of replacements of the identified sewer service replacements, all sewer main will be interior lined to enhance the longevity of the underground utility along Skyview Street. All roads will be patched with asphalt and all disturbed turf areas will be restored upon completion.

CONSTRUCTION TIMELINE
April 2024 - July 2024

Week of 06/24/2024

Completion of curb and gutter repairs on all streets. Once curb has been cured, restoration behind the curb will be completed.

Week of 07/01/2024
Start of roadway repairs.

Important Upcoming Dates
04/08/2024 - Start of construction
05/20/2024 - Completion of Water on Skyview and Start of Water on Vanden Bergh
06/14/2024 - Completion of Water on Vanden Bergh
07/15/2024 - Completion of all work & restoration

             

Road Closures, Vehicles & Traffic
For all construction, the road will remain open to a minimum of one-lane of travel. Slight delays may be encountered due to construction equipment using the area. Be attentive of construction workers directing traffic through the construction zone.

Vanden Bergh Business Access
Business access will be maintained as much as possible during construction. We intend to keep driveways open to each business at all times but may need to temporarily close one due to service location. Prior communication will occur if access will be unobtainable. Please contact the Construction Manager if you require special access needs.


Communication:
It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation @920-491-9081. As project manager, Cedar is most familiar with the daily operations of construction and can resolve many issues quickly.

If something happens after normal work hours that you feel requires immediate attention, please contact our On-Call Laborer @ 920-371-0744, and arrangements will be made to resolve the issue. As always, in an emergency, please call 911.

2023

     

Sal St. & Industrial Dr. - Sanitary Sewer - E23

 

UPDATE: Thursday, December 1, 2023.

Construction consists of sanitary sewer main replacement and service replacements to the right of way at previously identified properties. Upon completion of replacements, all sewer main will be interior lined to enhance the longevity of the underground utility. All roads will be patched with asphalt and all disturbed turf areas will be restored upon completion.

CONSTRUCTION TIMELINE
October 2023 - May 2024

Week of 12/04/2023

Sewer Contractor to finish sanitary service replacements. Asphalt Contractor to finish restoration on all work that has been completed.

Week of 12/11/2023
Sewer Contractor working on temporary restoration and demobilizing from the site.

Important Upcoming Dates
01/08/2024 - Start of Cured in Place Pipe Lining
03/01/2024 - Completion of Cured in Place Pipe Lining
05/15/2024 - Completion of all work & restoration

             

Road Closures, Vehicles & Traffic
For all construction, the road will remain open to a minimum of one-lane of travel. Slight delays may be encountered due to construction equipment using the area. Be attentive of construction workers directing traffic through the construction zone.

Business Access
Business access will be maintained as much as possible during construction. We intend to keep driveways open to each business at all times, but may need to temporarily close one due to service location. Prior communication will occur if access will be unobtainable. Please contact the Construction Manager if you require special access needs.


Communication:
It is the intent of the Village to minimize the amount of disruption and inconvenience to the community during any construction process. If during normal work hours you feel something went unnoticed, or needs attention, please contact Cedar Corporation @920-491-9081. As project inspector, Cedar is most familiar with the daily operations of construction and can resolve many issues quickly.

If something happens after normal work hours that you feel requires immediate attention, please contact our On-Call Laborer @ 920-371-0744, and arrangements will be made to resolve the issue. As always, in an emergency, please call 911.

2026

     

Hoffman Road
Bellevue St. to Monroe Rd.

UPDATE: Monday, May 20, 2024

The proposed project would involve improvements to the 0.7-mile section of Hoffman Road between Bellevue Street (County XX) and Monroe Road (County GV). The project is located on the west side of the Village of Bellevue in Brown County.

Public Involvement Meeting
May 15, 2024 - July 5, 2024
Presentation
Public Comment Form


Project Schedule
Public Involvement - May 15, 2024 - July 5, 2024
Preliminary Plans - April 2024
Environmental Document - July 2024
Final Plans - August 2025
Construction would be scheduled for 2026

2026

     

Ontario Road Reconstruction
Eaton Rd to North Village Limits

UPDATE: Monday, May 20, 2024

The proposed project would involve improvements to an approximately 0.50-mi. segment of Ontario Road between Eaton Road (County JJ) and the North Village Limits. The project is located on the east side of the Village of Bellevue in Brown County.

Public Involvement Meeting
May 15, 2024 - July 5, 2024
Presentation
Public Comment Form


Project Schedule
Public Involvement - May 15, 2024 - July 5, 2024
Preliminary Plans - March 2024
Environmental Document - August 2025
Construction would be scheduled for 2026